A VISION OF TRANSPARENCY

construction

2.5 mil

COST PROJECTION

750K

FUNDS RAISED

SINCE 2014

1.75 mil

funds/donations

NEEDED

renovation

14month

TIMELINE

2023

SPRING

SCHOOL OPENING

THE PROCESS

  1. ARCHITECTURAL AND MEP (MECHANICAL, ELECTRICAL, PLUMBING) PLAN UPDATE AND REVISION FOR SUBMISSION TO CITY

  2. SUBMIT UPDATED PLANS TO CITY FOR REVIEW AND APPROVAL (1-3 MONTH PROCESS)

  3. OBTAIN CONTRACTOR PRICING FOR ALL SCOPES

  4. FORM SCHEDULE/TIMELINE FROM CONTRACTOR MATERIAL LEAD TIMES AND LABOR SCOPE PROJECTIONS (8-10 MONTHS)

  5. 1 - 2 MONTH ADDITION TO SCHEDULE FOR TRADE INSPECTIONS

  6. CREATE OPERATIONAL BUDGET FOR SCHOOL TO CREATE COST AND DONATION PROJECTIONS (Day/Month/Year)

  7. ADVISE ON OVERALL CONSTRUCTION AND RENOVATION COST PROJECTION

  8. UPDATE DONATION FUNDS AND PROVIDE DEDUCTION TO CONSTRUCTION BUDGET AND OPERATIONAL BUDGET

 A DREAM TO MANIFEST INTO REALITY

Black Fasde.fw.png

THE SCHOOL

THE CLASSROOM

THE GYM
(NAT TURNER)

THE CAFE

DONATIONS

GABRIEL DOUGLASS  & STEVEN HARVEY ACADEMY

"Don't Hit The Cashapp...Invest In The Future Of Our Future"